Acme Solar Holdings Announces Commissioning of First Phase of Battery Energy Storage System Project
Acme Solar Holdings Limited announced the commissioning of the first phase of a Battery Energy Storage System (BESS) project located in Jaimalsar, Bikaner, Rajasthan. The project is being executed by ACME Surya Power Private Limited, a wholly-owned subsidiary of Acme Solar Holdings Limited.The initial phase of the BESS project includes 60 MW of capacity with 269.606 MWh of storage. The overall project has a planned capacity of 250 MW and 1103.392 MWh.
The commercial operation date for this first phase is scheduled for March 25, 2026.
| Metric | Value |
|---|---|
| Project Capacity (Phase I) | 60 MW / 269.606 MWh |
| Total Project Capacity | 250 MW / 1103.392 MWh |
| Location | Village: Jaimalsar, Dist: Bikaner, State: Rajasthan |
| Subsidiary | ACME Surya Power Private Limited |
| Commercial Operation Date (Phase I) | March 25, 2026 |
Source:
Disclaimer: Due care and diligence have been taken in compiling and presenting news and market-related content. However, errors or omissions may arise despite such efforts.
The information provided is for general informational purposes only and does not constitute investment advice, a recommendation, or an offer to buy or sell any securities. Readers are advised to rely on their own assessment and judgment and consult appropriate financial advisers, if required, before taking any investment-related decisions.