Solarworld Energy Solutions Limited Receives BESS EPC Project from NTPC

Solarworld Energy Solutions Limited Receives BESS EPC Project from NTPC

Solarworld Energy Solutions Limited Receives BESS EPC Project from NTPC​

Solarworld Energy Solutions Limited announced on March 29, 2026, that it has been awarded an Engineering, Procurement and Construction (EPC) package for Battery Energy Storage System (BESS) implementation at the Solapur Super Thermal Power Station (Lot-1). The contract was awarded by NTPC Limited.

The project, titled 'BESS Implementation at NTPC Thermal Power Stations (Lot-1),' has an award capacity of 132 MW/264 MWh. The value of the order is approximately INR 314.26 crore (excluding taxes). The project execution timeframe is 15 months.

According to details released, the BESS EPC project is a domestic order and does not involve any related party transactions.

Project Details
The following table summarizes key details of the awarded contract:
ParticularsDetails
Awarding EntityNTPC Limited
Project DescriptionBESS Implementation at NTPC Thermal Power Station (Lot-1) at Solapur Super Thermal Power Station
Order ValueApproximately INR 314.26 crore (Excl. Taxes)
Capacity132 MW/264 MWh
Project TypeBESS Engineering, Procurement and Construction (BESS EPC)
Execution Timeframe15 Months
Related Party TransactionNo

Source:​

 

Disclaimer: Due care and diligence have been taken in compiling and presenting news and market-related content. However, errors or omissions may arise despite such efforts.

The information provided is for general informational purposes only and does not constitute investment advice, a recommendation, or an offer to buy or sell any securities. Readers are advised to rely on their own assessment and judgment and consult appropriate financial advisers, if required, before taking any investment-related decisions.

Back
Top